Update: Shoring in the Roadway at Leaside Station

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
March 1, 2017

What Work is Taking Place?

Beginning in early March, crews will start support of excavation work, also known as shoring, in the city right of way at the future Leaside Station.  The station is located at the intersection of Bayview Avenue and Eglinton Avenue East.  Steel piles as well as braces and tie-backs will be installed around the perimeter of the station box and entrances to support excavation.  Once steel piles are installed in each area, shallow excavation occurs and wooden decking is installed over the excavated area, followed by reinstatement of the roadway. 

Shoring work started at the main entrance location in January 2017. Right of way works will be conducted in four stages, beginning in the roadway on the south and southeast side of Eglinton Avenue East. 

Timing
  • Work is expected to begin as early as March 3rd, 2017 and will continue for approximately fifteen (15) months. 
  • Work is permitted between the hours of 7:00 AM and 11:00 PM, 7 days a week. Crews will be working until 11:00 PM on a regular basis.
  • Occasional overnight work may be required – Metrolinx and CTS will notify the public in advance and monitor activities throughout.
  • Work is subject to permits and all relevant approvals, and may be rescheduled due to weather conditions or unforeseen circumstances.
What to Expect
  • Nearby residents and businesses can expect noise in the area caused by a pile drill, crane, loaders, trucks and other construction equipment, as well as dust from drilling activity and debris removal.
  • Heavy truck traffic, entering and exiting the work zone, and traveling through nearby streets can be expected.
  • In addition to construction activity, residents can expect to see equipment and material storage within designated work zones.
  • For safety purposes, fencing will be erected around the work zone.

 

Stage One

Stage 1 Details for Leaside Shoring
Stage One Details
Traffic:
  • Lane reductions will be in place, but at least one lane of traffic will be maintained in all directions. 
  • Northbound right turn will be restricted (Bayview Ave. northbound to Eglinton Ave. eastbound).
  • Westbound left turn will be restricted (Eglinton Ave. westbound to Bayview Ave. southbound).
  • Left turns will be prohibited from the parking garage egress for the 1750 Bayview Avenue condominium. 
Pedestrians:
  • There will be no pedestrian access from Eglinton Ave to Bayview Ave on the southeast corner of the intersection.
  • The north-south crosswalk on the east side of Bayview Ave and the east-west crosswalk on the south side of Eglinton Avenue will be shifted slightly back from the intersection.
  • Overhead protection for pedestrians will be in place at various locations near the work zone.
  • All crosswalks will remain open. 

 

TTC Details

To accommodate ongoing work at Leaside Station, four (4) TTC bus stops on the corners of Eglinton Ave East and Bayview Ave was relocated; this will remain for stages one and two. One (1) TTC bus stop will be closed. 
TTC Details for Stage 1 shoring

 

For more information, please contact Nicole DiCarlo at the East Community Office.

Thank you for your patience as we work to build this important project.

 Please support your local businesses during construction.

Sign up to receive regular email updates. 

 

Please CLICK HERE to see the permit.

Please CLICK HERE to see the permit.