Yonge Street

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
June 142017

Eglinton - Mount Pleasant Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant Stations was held on June 13, 2017. You can see the presentation here:

Read more »

June 092017

Dewatering System Installation Eglinton Avenue East from Lillian Street to Redpath Avenue

What Work is Taking Place

The term “dewatering” means pumping from the ground water at a site where there will be excavation.  At Eglinton Avenue East between Lillian Street and Redpath Avenue, half a dozen small wells will be drilled for the future Cross Passage. The volume of soil that requires dewatering is significant.  The wells will be drilled and shallow trenches will be required to lay the pipes, pumps, wells and valves to do the work.   Read more »

May 022017

Upcoming Works at Eglinton Station: Utilities Relocations – Stage 3

What Work is Taking Place

Work to replace and relocate existing utilities continues to make way for the future Eglinton interchange station. Storm and sanitary sewers, water mains, hydro ducts, and telecommunications utilities are being replaced and relocated in a series of stages. During this third stage, work will take place on the south side of Eglinton Avenue, east and west of Yonge Street. Read more »

April 202017

UPDATE: Demolishing the Abandoned TTC Bus Depot

What Work is Happening?

  • The abandoned TTC Bus Depot (pictured below) is being demolished to make way for the new Eglinton LRT Station’s primary entrance (pictured at bottom) and new developments at Yonge and Eglinton.

Progress to Date

  Read more »

March 292017

Overnight Tunnel Boring Machine Removals Eglinton Avenue Closure: Yonge St. to Dunfield Ave. Nightly, April 4-7 & April 10, 2017

What Work is Taking Place?

Tunnelling is complete, and crews will be removing the south TBM, Humber, over several days in April, 2017 (April 4, 5, 7 and 10).  As with Don, Humber will be disassembled and removed in pieces. The pieces will be loaded onto trucks by large cranes and transported offsite. Read more »