June 122015

Update: Eglinton Avenue East Extraction Shaft Work In North Lanes

What: Work continues at the extraction shaft on Eglinton Avenue between Yonge Street and Lillian Street. The next stage of work is set to begin, which will remain on the north lanes of Eglinton Avenue. This work will include, heavy civil construction; installation of secant piles, jet grouting, daylighting and relocating utilities. Read more »

March 122015

Yonge & Eglinton Avenue East Extraction Shaft Work Shifting to North Lanes

What: Work on the construction of the tunnel boring machine extraction shaft located within the Eglinton Avenue roadway on the east side of Yonge Street continues. The next stage of work is set to begin, and will involve construction shifting back to the north lanes of Eglinton Avenue. This work will include daylighting and relocating utilities.

  Read more »

March 062015

Yonge & Eglinton Avenue East Extraction Shaft Work Shifting to Centre Lanes

What: Work on the construction of the tunnel boring machine extraction shaft located within the Eglinton Avenue roadway on the east side of Yonge Street continues. The next stage of work is set to begin, and will involve construction shifting to the centre lanes of Eglinton Avenue. This work will include daylighting and relocating utilities.

When: Work shifting to the centre lanes is expected to start as soon as March 9, 2015. Timelines may be adjusted due to weather conditions and/or unforeseen circumstances.  Read more »

February 122015

Monitoring Equipment Installation Work near Yonge Street: Temporary Closure of Southbound Holly Street from Eglinton

What we are building

What: Crews will be installing monitoring equipment on the west side of Holly Street, just south of Eglinton Avenue. This work is required prior to building support headwalls and an extraction shaft within the Eglinton Avenue roadway on the east side of Yonge Street, and is in addition to the current construction activities on the north side of Eglinton Avenue.   Read more »

January 162015

Extraction Shaft Construction Work East of Yonge Street Shifting to North Side of Eglinton Avenue

What: Crews will be working on the construction of a large shaft including the building of support piles and a headwall, located within the Eglinton Avenue roadway on the east side of Yonge Street. 

Why: Crews are currently relocating utilities on the south side of Eglinton. During the next stage, construction of a large shaft will begin on the north side of Eglinton. Construction of this shaft will include daylighting for utilities, installation of piles, jet-grouting and excavation and decking of the roadway.   Read more »

January 082015

2014 Year-in-Review

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilmetre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today. Read more »

January 082015

Retour sur l’année 2014

Le projet Eglinton Crosstown est une ligne de transport léger sur rail (TLR) de 19 kilomètres qui longera Eglinton Avenue au cœur de Toronto et comprendra un tunnel souterrain de 10 kilomètres dans sa section centrale. Lorsqu’elle sera terminée, la ligne reliera Mount Dennis, à l’ouest, à Kennedy Road, à l’est, et offrira un service jusqu’à 60 % plus rapide que le service d’autobus actuel.  Read more »

December 052014

Utility Relocation Work near Yonge Street for Extraction Shaft - Temporary Closure of Holly Street

What we are building

What: Crews are working on advanced utility construction and relocation prior to the building of support headwalls and an extraction shaft, located within the Eglinton Avenue roadway on the east side of Yonge Street.  Read more »

November 172014

Cross Passage Construction Update – November 2014

Information as of November 5, 2014

What is the Crosstown?

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today. 

Did you know? Read more »