What's New?

 
Syndicate content
 
September 07 2018

UPDATE: Upcoming Traffic & Pedestrian Changes at Eglinton Station

What Work is Taking Place?

Support of excavation work, also known as shoring, has commenced to make way for the future Eglinton interchange station. This work will include pile installation, jet grouting and road deck installation. Shoring at the TTC bus depot and along south side of Eglinton has been complete. The work is carried out along the north side of Eglinton.

The next phase (depicted below) will take approximately 3-4 months to complete. The entire shoring process will take approximately twenty-four (24) months to complete. Read more »

September 05 2018

UPDATED: Support of Excavation Works at the North End of Kennedy GO Station Platform as Part of Eglinton Crosstown LRT

What Work is Taking Place?

As part of continued support of excavation works (shoring) for the future Kennedy Station, crews will continue work on the north end of the GO platform as part of the GO Transit improvements.

To facilitate these improvements, installation of support of excavation are also being made to the GO Transit Stouffville Corridor at Kennedy GO Station starting as early as Saturday, September 8, 2018. Read more »

August 31 2018

Construction Notice - Leaside Station - Sidewalk Closure

SIDEWALK CLOSURE AT LEASIDE STATION

 

What Work is Taking Place? Read more »

August 31 2018

UPDATED: Pre-cast Concrete Installation for Facility Services Building Construction at Eglinton Station

What Work is Taking Place?

Beginning as early as September 8, 2018, crews will install pre-cast concrete for the Facility Services Building for the TTC Line 1 Subway system . Crews will also undertake various activities inside the TTC station. Read more »

August 31 2018

Avenue Station Construction Updates

MINING UPDATE

Mining operations are underway at both the Secondary Entrance and the Main Entrance sites. Mining occurs on a 24 hour schedule. Starting in early September, mining will occur on a 24 hour schedule, 7 days a week. Read the construction notice for more detail.

 Secondary Entrance Read more »

August 30 2018

Watermain Lining & Valve Installations at Oakwood Station - September & October 2018

WHAT WORK IS TAKING PLACE?

To increase the durability of local watermains during mining operations at Oakwood Station, sections in the vicinity of station construction zone will be lined. Lining of the watermain is a minimally invasive method of repair and rehabilitation that is commonly used throughout the City of Toronto. Using this process allows us to complete the work without excavating the entire watermain through the road.  As part of the watermain work, a number of valves will also be installed along Eglinton Avenue between Times Road and Alameda. Read more »

August 29 2018

UPDATED: Wilson Brook Culvert Work Begins East of Future Sloane Stop

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue, work on the Wilson Brook Culvert will be taking place on the south and north side of Eglinton Avenue in front of 1730 Eglinton Avenue East. This work is expected to begin as early as Wednesday, August 16 to December 15, 2018.

Crews will be building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. Read more »

August 29 2018

UPDATE: Overnight Water Outage Notice on Eglinton Avenue East - August 29-30, 2018

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories:
August 29 2018

UPDATE: Watermain, Storm and Sanitary Relocation at Kennedy Station Ionview Road to Kennedy Road

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between Ionview Road and Kennedy Road.

 Crews continue to work on installing the new storm and sanitary system from Ionview to Kennedy and will complete their work with a final connection to the existing manholes located within the Kennedy and Eglinton intersection. Read more »

August 27 2018

UPDATE: Overnight Temporary Water Shutoff on Eglinton Ave E between Pharmacy and Warden - Aug 29 & Aug 30

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road; the work commenced August 20th and will last for approximately four (4) weeks. In order to complete this stage of work a water outage is required. Read more »

Categories: