March 05 2018

Equipment Move at Caledonia Station

What Work is Taking Place?

On Monday March 5 and Tuesday March 6, crews will perform maintenance of the water tank at Caledonia Station. The water tank is part of the station’s dewatering system, which removes ground water to make way for excavation.  Read more »

March 02 2018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:

Read more »

March 02 2018

Sidewalk Repairs at Leaside Station

WHAT WORK IS TAKING PLACE?

On Monday, March 5th Leaside station crews will complete repairs on a section of sidewalk on the north side of Eglinton Avenue between Bayview Avenue and the Metro driveway. 

 Read more »

March 02 2018

OVERNIGHT WORK TO PREPARE FOR WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

ORIGINAL POST: FEBRUARY, 16, 2018

RE-ISSUE DATE: MARCH 2, 2018

WATERMAIN LINING OVERVIEW Read more »

March 01 2018
March 01 2018

Cedarvale & Forest Hill Construction Liaison Committee Meeting

The construction liaison committee meeting of Cedarvale and Forest Hill stations was held on February 28, 2018. You can see the presentation here:

Read more »

February 28 2018

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on February 27, 2018. You can see the presentation here: 

Read more »

February 28 2018

Special Pile Installation at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are currently completing support of excavation (or shoring) on the north side of Eglinton. As part of this work, two special polymer piles (vertical steel beams) will be installed.  Special polymer piles are large in depth and size.  Therefore, a longer drilling and concrete pouring period is required. To ensure the structural integrity of each pile, once installation begins, it cannot be stopped. Read more »

February 27 2018

UPDATE: Overnight Work for GO Transit Improvements at Kennedy and Partial Closure of Southern Section of East Platform

Originally Published: February 8, 2018

Updated: February 12, 2018, February 16, 2018 and February 27, 2018

What Work is Taking Place?

Kennedy Station and its environs are changing every day.

As part of GO Transit Improvements at Kennedy, crews will close a southern portion of the existing east platform on the Stouffville Line as early as Monday, February 19, 2018 to facilitate shoring for the GO underpass, the construction of a new pedestrian underpass, and the shoring for the Eglinton Crosstown LRT Box under the GO corridor. Read more »

February 27 2018

Overnight Piling Work February 28 for Science Centre Station

What Work is Taking Place?

Crews will be drilling piles within the Don Mills Road and Eglinton Avenue East intersection as part of the Support of Excavation work at the future Science Centre Station. 

Due to the location of the piles and in an effort to minimize disruption to local traffic and commuters work will be performed overnight on Wednesday, February 28, 2018 from 8:00 p.m. to 5:00 a.m. Thursday morning. The intersection will be restored in advance of morning rush hour. Read more »